Procedures for building Garage
1.Concrete Foundation:: y$ R4 z* ?% x9 J
a.land Flating: Need roller and pressor and get earth compaction index to civil technical requirement
. D* x( J/ c2 v1 qb.Footings: need about 16"x8"footing reinforced with 3-15M steel Rebar continuously and 15M transverse rebar at 12" spacing
1 b+ M1 A7 j. U. \c. Concrete wall: about 8" wide by 36" heigh reinfored with 15M vertical rebar at 12" spacing and 3-15M horizontal rebar 2 ^. V5 a# {* O u* o& X
d. Slab: about 5"-6" slab reinforced with 10M rebar at 12" spacing each way2 H/ v% T) |: d! I, k" H
e. order concrete mix from Lafarge or Inland concrete ready mix ) o: v9 a, o9 D/ K
f.pour concrete first footing, wall and last slab.
8 H$ ?, E' a, i3 I3 G- }' v9 J: D! I! T2 y" f: j2 ~
After 3days later (better 7days) you can start framing with wood and dry wall, and insulatin materials
. u" F1 H9 V8 i. K7 A' @- f/ N# I9 ~% O1 j, f6 b6 I
All of them you need have roughly design and sketch. Estimate materials. |
|